This Request for Proposals (the "RFP") is an invitation by the Government of Bermuda (the "Government") to prospective proponents to submit proposals for Retaining Wall Middle Road Southampton as further described in Section A of the RFP Particulars (Appendix D) (the "Deliverables").
The Ministry of Public Works and Environment is seeking to engage a suitable qualified and experienced contractor to construct a retaining wall to stablize a portion of Middle Road, Southampton.
RFP Contact
For the purposes of this procurement process, the "RFP Contact" will be:
Mr. Austin Kenny, Principal Engineer (Structures Section), email: avkenny@gov.bm
Important Dates
Issue Date of RFP | Wednesday July 23, 2025 |
Pre-Bid / Site Meeting | Wednesday July 30, 2025 10:00 AM |
Deadline for Questions | Friday August 08, 2025 |
Deadline for Issuing Addenda | Tuesday August 12, 2025 |
Submission Deadline | Thursday August 21, 2025 03:00:00 PM |
Rectification Period | 3 business days |
Anticipated Ranking of Proponents | Thursday August 28, 2025 |
Contract Negotiation Period | 7 calendar days |
Anticipated Execution of Agreement | Thursday September 04, 2025 |
*All times listed are in Bermuda local time.
Pre-Bid / Site Meeting
A mandatory Pre-Bid meeting has been scheduled for this procurement. The purpose of the Pre-Bid meeting is to provide a structured and formal opportunity for the bidders to raise questions and clarify any of the proposal requirements and procurement process.
The date, time and location are provided as follows:
Date: 30 July 2025
Time: 10:00 A.M.
Location: Adjacent to 118 Middle Road, Southampton
** Absolutely no verbal questions/clarification will be acknowledged.
***Late submissions will not be accepted.