Development of a utility-scale solar photo-voltaic installation
The Ministries of Economic Development and Public Works of the Government of Bermuda are in the process of developing an RFQ and RFP for the development of a utility-scale solar photo-voltaic installation on ‘the Finger’ at the L.F. Wade International Airport.
Communications Protocol:
If you wish to be added to the email distribution list for this project please email airportsolarproject@gov.bm with your preferred email address, name and company name.
All questions and or queries related to this project must be emailed to airportsolarproject@gov.bm. Questions sent to this email address will be posted anonymously to a Questions and Answers document - 31/08/2016, if and when they can be answered. Individual responses will not be provided.
To ensure all interested parties have equal access to information related to this project, all relevant information will be posted to this website only.
Accordingly, NO Department of Energy, Department of Works and Engineering, Ministry, BELCo Staff or our Consultants will answer any questions related to this project which are not emailed to the address above.
Actions |
Dates and Times |
Stakeholders Presentation Event |
March 24th 2016 |
Stakeholders Networking Event |
June 3rd 2016 |
RFQ Issued (see Related Documents section below) | August 17th 2016 |
RFQ Deadline for Clarification Questions on RFQ | August 31st 2016 5pm ADT |
RFQ Qualifications Submission Deadline | September 14th 2016 5pm ADT |